BIM Based Time Management Among Construction Contractors in Turkey
An Interview Study
Abstract
In both developing and industrialised countries, due to numerous time-related problems of construction projects, BIM-based time management, 4D BIM, plays an increasingly critical role within the industry. This study investigates the planning and scheduling problems, BIM application level, and BIM-based scheduling implementation by the lead construction companies in Turkey.
Despite the critical importance of the planning department in construction companies, the planning and BIM integration levels have scarcely been investigated from the contractor perspective in Turkey.
This paper presents the outcomes of 16 semi-structured interviews (SSI) with managers of the leading Turkish contractors selected from 100 of ENR’s 2019 Top 250 International Contractors list; a list of issues are outlined. The current situation escalates problems like tendering with missing project documents, examining 2D project drawings while scheduling, fragmentation, project manager’s reluctance to use and follow the project schedule, issues with updating the schedule as per construction improvements and quantities, and a lack of investment for BIM implementation. The research findings, ultimately, aim to help contractors improve their processes. Although this study’s findings are obtained from interviews with lead Turkish contractors, it is not limited in terms of geographic context since the interviewed contractors work worldwide.
Keywords:
BIM, 4D, time management, construction, TurkeyPublished Online
How to Cite
Issue
Section
License
- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution License that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work (see The Effect of Open Access). As soon as the paper is accepted, finally submitted and edited, the paper will appear in the "OnlineFirst" page of the journal, thus from this point no other internet-based publication is necessary.